Case Study – Norcroft Trading Co


Project Overview

Client: Norcroft Trading Co (on behalf of Allen Bartlett and Sons Chatteris)
Location: Chatteris
Project Duration: August 2021 – October 2021
Scope of Work: Full factory clearance, including the removal of machinery, equipment, and waste from the site.

Objectives

The primary objectives of the factory clearance project were to:

  • Safely and efficiently remove all machinery and equipment from the Allen Bartlett and Sons facility.
  • Ensure minimal disruption to surrounding operations.
  • Adhere to strict safety and environmental regulations.
  • Complete the project within the agreed timeframe.

Project Description


SKH Machine Removers & Son Ltd was contracted by Norcroft Trading co for their client Allen Bartlett and Sons to conduct a full factory clearance of their Chatteris site. After a detailed assessment and quotation, the project commenced in August 2021.

Key Phases of the Project:

1. Initial Assessment:

  • Conducted a thorough inspection of the site to identify the machinery and equipment to be removed.
  • Developed a comprehensive plan that included timelines, resource allocation, and safety protocols.

2. Preparation and Planning:

  • Coordinated with Norcroft and Allen Bartlett and Sons to schedule the clearance during off-peak hours to minimize disruption.
  • Secured necessary permits and ensured compliance with local regulations.

3. Execution:

  • Mobilized a skilled team equipped with the necessary tools and machinery for the removal process.
  • Cleared the site in phases, starting with larger machinery and followed by smaller equipment and debris.
  • Implemented strict safety measures to protect workers and the environment.

4. Loading and Transportation:

  • Organized logistics for transporting machinery and equipment to designated disposal or resale locations.

5. Site Cleanup:

  • Conducted a thorough cleanup of the site post-clearance, ensuring that all debris and waste were removed.

Challenges Faced


  • Logistical Coordination: Managing the transportation of large machinery required careful planning to avoid delays.
  • Safety Regulations: Adhering to safety protocols was paramount, especially when handling heavy equipment.
  • Time Constraints: Completing the project within the three-month timeframe required efficient execution and teamwork.
  • Access: No entrance of any value was fixed by removing a small portion of the internal walls, even then we could only work our way through the machinery as it all too compacted with machinery in the building

Results


  • Successfully completed the factory clearance on schedule, allowing Allen Bartlett and Sons to proceed with their future plans for the site.
  • Maintained a high standard of safety throughout the project, with no accidents or incidents reported.
  • Client satisfaction was achieved, resulting in positive feedback and potential future collaborations.

Conclusion


The full factory clearance project for Norcroft & Allen Bartlett and Sons exemplifies SKH Machine Removers & Son Ltd’s commitment to efficiency, safety, and client satisfaction.